WESTERN RAILWAY GEARS UP FOR MONSOON

No.2018/05/Mumbai, May 09, 2019

WESTERN RAILWAY GEARS UP FOR MONSOON

 

Various additional steps taken to ensure smooth train operations

          

In order to keep the wheels of all trains running and to ensure uninterrupted services during ensuing monsoon, pre-monsoon preparation works are going o­n in Western Railway in full swing. Considering the experience in the previous monsoon in Vasai-Virar sector alongwith various other areas, additional steps have been taken to ensure smooth operations during monsoon.

According to a press release issued by Shri Ravinder Bhakar – Chief Public Relations Officer of Western Railway these works include cleaning and desilting of culverts, desilting of side-drains, installations of high-power diesel & electric pumps, special maintenance of infrastructure, etc.These works will be completed by 1stJune 2019 in the first phase. 2nd phase of culverts and drain cleaning shall be undertaken from 1st June, 2019 o­nwards.

Analysis of Rainfall and Flood prone areas:

Western Railway has identified flood-prone areas o­n its suburban section. Based o­n this analysis, extra attention will be given to certain sections which are potentially low-lying area and are thus likely to be inundated. These areas have been identified as tracks/yards of Grant Road, Elphinstone Road, Dadar, Matunga Rd-Mahim, Bandra-Khar, Andheri-Jogeshwari and Vasai-Virar sections.

Western Railway has also compiled the data from Tide-table wherein dates of high tides of more than 4.0 meters during ensuing monsoon, between 1st June, 2019 to 30th Sept, 2019, have been included. This will help in taking necessary precautions as and when required.

Special Pre-monsoon Action& Action to be taken during monsoon:

ØOf the 53 culverts existing in Churchgate-Virar suburban section, first round of desilting in 37 culverts has been completed, while balance 16 shall be completed by 20/05/2019. 2ndround of desilting will be done after conducting Joint inspection of first round in month of June 2019 & subsequently, in August 2019. Remaining major culverts will be got cleaned by MCGM officials and these include Mithi river, Dharavi Nallah, Poisar nallah, etc. Joint inspection are also being carried-out by Western Railway and MCGM officials.

ØLifting of tracks in low-lying areas has already been completed in Mahim Yard o­n Harbour lines, o­n Bandra-Khar Down slow line where water-logging has been observed in previous years. Lifting of track upto 200 mm is to be carried out in Vasai-Virar section and this work is in progress and will be completed by 25.05.19.

ØLowering of cess alongside of tracks is under progress. Approx 1,60,000 cum muck has been lifted by deploying JCB, Poclain, manual labour and specially-designed muck special EMU train. This activity will ensure smooth flow of storm-water during monsoon.

ØWR has installed about 154 high-power pumps at vulnerable low-lying locations such as Marine Lines, Mumbai Central, Dadar, Matunga Road, Mahim, Bandra, Andheri, Borivali, Nalasopara, Virar etc.

ØWR has also undertaken the work of desilting of side-drains. 60% of drains have already been cleaned. This work will be completed by 25.05.19. Subsequent round of cleaning will be undertaken in July and August, 2019 as per requirement.

ØWestern Railway has come up with an instruction booklet for Monsoon precautions called monsoon booklet for its Officers, supervisors and station staff. This book not o­nly mentions the flood-prone areas and important dates of high tides, but it also gives details of precautions to be taken during such situations. It also has comprehensive details of telephone numbers of Officials dealing with disaster management, important telephone numbers of Railway Officers, Supervisors & civil officials such as MCGM, NDRF, Weather Bureau, Hospitals etc.

ØIn order to ensure running of trains during monsoon, special attention is also being given to maintenance of Overhead electric equipments. This includes cleaning of insulators, checking of protective screens o­n FOB/ROB, protection of contact and catenary wires and earthing.

ØJoint survey for Cutting & trimming of vulnerable trees existing in the vicinity of track has been done by MCGM & WR officials. Necessary cutting & trimming will be completed by 25.05.19.

ØWR has also taken-up monsoon-related maintenance work of its EMU suburban rakes which include detection & plugging of possible leakages in EMU coaches and their electrical equipment, smooth movements of windows & doors etc. Work of cleaning of roof of coaches and insulators has also been taken-up.

ØInsulation testing of various signalling gears will be completed before o­nset of monsoon and wherever required, repairs/replacement shall be carried-out.

ØMonsoon protective gears viz, gum boots and rain coats to maintenance staff are being procured and shall be distributed before o­nset of monsoon.

ØStocking of sufficient maintenance spares before o­nset of monsoon is being ensured.

ØRunning of Muck specials which includes o­ne self propelled Muck spl. of EMU coaches to clear muck and garbage as and when required.

ØCleaning of drains at station and platforms to avoid water-logging in station premises.

ØSpecial trains carrying boulder and quarry dust are kept in readiness to deal with breaches & wash-out situation.

ØSpecial precautions are going to be taken at stations to monitor crowd build-up during water-logging by monitoring through CCTV and ensuring regular announcement as well as crowd-management.

ØRound-clock monitoring and manning of Mumbai Central control office by officers of various Depts during heavy rains and maximum high-tide days by deputing officers/supervisors at vulnerable locations.

ØProvision of May I help you booth in case of emergency to guide passenger will be opened at all vulnerable stations.

ØReal time updates o­n twitter to guide passengers.

ØRegular announcements at station.

ØStall owners have been instructed to keep adequate amount of stock during water-logging.

Coordination with officials of Municipal Corporation Greater Mumbai, Mira-Bhayander Municipal Corporation & Vasai-Virar City Municipal Corporation:

Pre-cleaning Joint inspections byWestern Railway and Municipal officials have been carried out. It also includes provision of pumps by municipal officials at locations where blockage in drainage is expected. A hotline communication has been set up between MCGM Disaster control and Western Railway Traffic control for quick communication during emergency.

There had been water-logging noticed in Virar-Nallasopara area during 2018 monsoon, which had adversely affected train movement for several hours and in order to ascertain the constraints to free-flow of storm-water in this area, following action has been taken: -

·Dredging and desilting of drain and nala running in parallel to railway track and connecting to Vasai-Vaitarna creek has been undertaken. Work is nearly 60% complete and remaining is targeted to be completed by 30/05/2019.

·Desilting of culverts crossing track has been undertaken by using suction pump/desludging machine. Approximately 70% of culvert have been cleaned and rest are targeted to be completed by 25/05/2019.

·3 new underground drains has to be constructed between Vasai-Virar section for facilitating flow of storm-water during monsoon. Two nos. will be completed before 30/05/2019.

·IIT Mumbai had been consulted for hydrological survey of entire topography of Virar-Nallasopara section and report has been received and being studied for further implementation. Action will be taken shortly so as to avoid any water-logging during ensuing monsoon.

·Aerial survey by drone of Virar-Nallasopara area has been planned and shall be undertaken from 15.05.2019 o­nwards so as to ascertain the reasons for constraints to free-flow of storm-water.

·In addition to cleaning of existing culverts, construction of new culverts as well as widening of existing culverts are being undertaken in Virar-Nallasopara area.

1.Indian Metrological Department is shortly going to install Automatic Rain-Gauge at 06 stations viz. Ram Mandir, Mahalaxmi, Bandra, Dahisar, Mira Road and Bhayander for which necessary infrastructural support has been provided by Western Railway. Through these equipment, it shall be possible to do real time o­nline monitoring of rainfall.

 

 

*******





  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.