WR Press Release No 2020/07 30-07-2020
Mumbai
W. RLY SUCCESSFULLY REMOVED PERMANENT SPEED RESTRICTIONS IN BANDRA-KHAR SECTION OF MUMBAI DIVISION

                                                                                         Mumbai, 30th July, 2020

W. RLY SUCCESSFULLY REMOVED PERMANENT SPEED RESTRICTIONS IN BANDRA-KHAR SECTION OF MUMBAI DIVISION

The successful completion of this major infrastructural enhancement, W. Rly will now be able to substantially improve the speed of both Suburban as well as Mail/Express trains

Photo Caption: The various views of the engineering work being undertaken at Bandra - Khar section for removal of Permanent Speed Restriction (PSR).

With the aim of improving mobility as well as enhancing safety & speed, Western Railway has carried out massive work during the lockdown period in Bandra - Khar section and has successfully removed Permanent Speed Restriction (PSR) in place, thereby, helping to improve the speed of both local & outstation trains.

According to a press release issued by Shri Sumit Thakur - Chief Public Relations Officer of Western Railway, with the successful completion of this major infrastructural enhancement, W. Rly will now be able to substantially improve the speed of both local as well as Mail/Express trains in down direction. W. Rly carried out the massive work of dismantling 17 turnouts and slewing & realigning of curves with renewal of 400 track m rails, 1200 sleepers in just 57 days, inspite of the o­ngoing lockdown, by deploying around 60 men o­n daily basis. After the completion of this work, the super elevation has been increased from 60 mm to 105 mm and this has enabled for the removal of PSR. Due to this engineering development, the 60 Kmph PSR from Km 14/22 to 16/01 in 1.191 Km has been relaxed to normal speed of 100 Kmph for 901 meter from Km 14/22 to Km 15/6 and Km 15/12 to 16/1 and 90 Kmph from 15/6 to 15/10-12 in balance 290 m. Net time saving is 90 Seconds due to this development.

*****





  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.